Summary
Caltrans' late comments forced two expensive design amendments on the freeway ramp project, though this one is fully grant-funded. Council members want to push the state to fix its slow review process.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jul 28, 2026.
Impact analysis
$124,927.19 more, bringing the Advantec contract to $876,103.51 — but no city general fund dollars.
Drivers using the Rosemead Blvd. freeway ramps, once the project reaches construction.
Taxpayers generally — grant money is still public money that could have been spent elsewhere.